Week Twenty-Three
(10/5-10/11)


The side porch is finally gone!


The round hole is the vent pipe for the
range; it will move 1,400 cubic feet
of air, and to make it quiet, the motor
mounts outside the house!

Getting ready to pour the steps
down from the main room.

Back of the house with the forms for
the steps

The laundry shoot!!! It runs through the
pantry, but I'll gladly give up the space!

After a couple of tries, the ceiling
in Julie's office vaults to about
11 feet!

Check out the tub in the master bath!

The outside electrical box--It's big!

Little back porch slab is poured.

And the steps down from the back!

Basic connections to the electrical panels.

Starting the drain pan in the master shower...

...and in the guest shower.